The Measure Q Bond was passed in November 2012. Please review the active project status and updates. Citizens of Solano County invested in their futures by voting to improve and expand the facilities of the Solano Community College District with the passage of the Measure Q Bond.

June 2019

Fairfield Campus Active Project Updates

B1000 Horticulture Modular Restroom

(Click to View Project Summary)

 

Horticulture – Phase 2 Restroom Building – Fairfield Campus

Description: New modular restroom building in orchard area.

Budget:  $401,000

Status: Construction in progress.  Bonding company completing building punch list items.

Completion Target: June 2019

B100 Library LRC

(Click to View Project Summary)

Library/Learning Resource Center – Fairfield Campus

Description: Replacement of existing Building 100 Library with new 59,252sf Library/LRC, demo of old Library and old portable buildings.

Budget:  $45,948,000 ($24,300,000 Measure Q; $20,148,000 State; $1,500,000 Redevelopment pass-through funds)

Status: Plans approved by DSA.  Project will be issued for bid upon receipt of State approval, likely in July.

Completion Target: December 2021

 

B300 Modifications – Mailroom & Graphics - Fairfield Campus

Description: Renovation for relocation of Campus Mailroom and Graphics operation into this building.

Budget:  $250,000

Status: RFP issued to firms in District's Architect Pool.  Construction anticipated December 2019 - March 2020.

Completion Target: March 2020

 FF Bleacher Replacement

Bleacher Replacement – Baseball & Soccer - Fairfield Campus

Description: Replacement of bleachers and related access improvements for DSA certification.  

Budget:  TBD

Status: BOT approval for Architectural Services on July 17. Construction anticipated summer 2020.

Completion Target: Summer 2020

Vacaville Center Active Project Updates

 VV Annex Corbels Removal

(Click to View Project Summary)

Vacaville Center Annex Building Corbels Removal - Vacaville Center

Description: Remove corbels and patch back exterior finish.

Budget:  TBD

Status: Design documents in progress.  Construction anticipated fall 2019

Completion Target: Fall 2019

 

 

Aeronuatics - Sewer Connection and Parking Expansion Project - Vacaville

Description: Connect septic system to City/County sewer line.  Add 16 spaces adjacent to existing parking lot.  

Budget:  $535,000

Status: Develop project schedule, and design documents in progress.

Completion Target: Summer 2020