Solano Community College

Project Updates

June 2017

Fairfield Campus Active Project Updates

 Bldg 1200 Theater Stage & Seating

(Click to View Project Summary)

Performing Arts Building Renovation – Fairfield Campus

Description: Renovation of 28,545sf building and 2,770sf addition.

Budget: $20,232,700 ($6,252,818 Measure Q; $219,882 Measure G; $13,760,000 State)

Status: Construction 99% complete. Punchlist items are in progress.  Move back into the building is in progress.

Completion Target: May 2017

Ribbon Cutting Ceremony:  August 16, 2017, 5:00 pm

 Rebecca Valentino

(Click to View Project Summary)

 

Costume Workshop – Fairfield Campus

Description: Improvements in Building 1800 to provide for a costume workshop.

Budget:  $95,000 Measure Q

Status: Construction in progress.

Completion Target: June 2017

 FF Campus Entry Sidewalk Diagram

(Click to View Project Summary)

Campus Entry Sidewalk Improvements Project – Fairfield Campus

Description:  Pedestrian sidewalk improvements from the campus south entry to the entry plaza and bus stop area near Building 600.

Budget: $251,640

Status:  Project will be issued for bid in June with construction contract approval anticipated in July.

Construction Start Target: July 2017

Completion Target: September 2017

New Science Bldg Rendering

(Click to View Project Summary)

Science Building – Fairfield Campus

Description: New Science Building, approximately 44,249sf

Budget: $37,600,000

Status: Increment 2 Building plans submitted to DSA.  Construction site fenced.  Utility locating trenching in progress.

Construction Start Target: August 2017; Groundbreaking August 8, 2017, 5:00 pm

Completion Target: November 2018

FF Substation 1 and 2

(Click to View Project Summary)

Electric Substation Replacement – Fairfield Campus

Description:  Replacement of electric substations 1 and 2.

Budget: $1,349,000

Status: Construction contract awarded.  Contractor has ordered substation equipment.

Construction Start Target: Thanksgiving Break 2017

Completion Target: January 2018

 Softball Bleacher Replacement

(Click to View Project Summary)

Softball Bleacher Replacement Project – Fairfield Campus

Description:  Replacement of bleachers and press box.

Budget: $505,000

Status: Construction contract awarded.  Waiting DSA plans approval to start construction.

Construction Start Target: TBD

Completion Target: TBD

Vacaville Center Active Project Updates

VV Biotech & Science Bio-Reactors
 

(Click to View Project Summary)

Workzone Cam for the SCC Biotechnology Project
This can be viewed best in Chrome or Firefox.

Photo Montage for the SCC Biotech Project

Biotechnology & Science Building – Vacaville

Description: New Biotechnology and Science building wing (approximately 32,000sf) being added to the Vacaville Center building.

Budget:  $34,300,000

Status: Construction 76% complete.  Landscaping, final painting, and installation of equipment in progress.  Bio-reactors received and are in process of being installed.  Upcoming:  Receipt and installation of furninture and equipment.

Completion Target: July 2017

Ribbon Cutting Ceremony: September 6, 2017, 5:00 pm

Vacaville Intersection Improvements
 

(Click to View Project Summary)

Vacaville Center Intersection Improvements Project - Vacaville

Description: This project will establish a signalized intersection at the Center and Annex main driveways.  Scope of work includes signalization, crosswalks, and related roadway and Annex parking lot improvements. 

Budget: $1,178,270

Status: Construction contract awarded.  Submittals in progress.

Construction Start Target:  June 2017

Completion Target: September 2017

VV Annex Classroom Bldg.
 

(Click to View Project Summary)

“Annex" Classroom Building Renovation – Vacaville

Description:  Renovation of 13,940sf classroom building.

Budget:  $4,570,000

Status: Design phase 50% complete.  Additional truss testing in June.

Construction Start Target:  December 2017

Completion Target:  May 2018
Vallejo Center Active Project Updates

Vallejo Autotech
 

(Click to View Project Summary)

Automotive Technology Design/Build Fly Thru Video

Workzone Cam for the SCC Autotech Project

Timelapse video for the SCC Autotech Project

Autotechnology Building – Vallejo

Description: New Autotechnology Building, approximately 30,000sf, located at the corner of North Ascot Parkway and Turner Parkway.

Budget:  $23,600,000

Status: Construction 70% complete.  Restroom partitions, overhead doors, and data cabling completed.  Suspended ceiling, storefront glazing, and site flatwork in progress.

Completion Target: August 2017

Ribbon Cutting Ceremony: September 20, 2017, 5:00 pm

VJ HVAC Replacement
 

(Click to View Project Summary)

 

Vallejo HVAC Upgrade Project – Vallejo

Description: Replacement of HVAC system at Vallejo Center Building.

Budget:  $2,175,024

Status: Construction in progress.  Center will be closed for the summer.  Summer school classes will be held at MIT and Georgia Street facility.

Construction Start Target: June 2017

Construction Completion Target: early August 2017