Solano Community College

Project Updates

June 2018

Fairfield Campus Active Project Updates

 B100 Library LRC

(Click to View Project Summary)

Library/Learning Resource Center – Fairfield Campus

Description: Replacement of existing Building 100 Library with new 59,252sf Library/LRC, demo of old Library and old portable buildings.

Budget:  $41,948,000 ($21,800,000 Measure Q; $20,148,000 State)

Status: Design in progress.  100% Design Development Documents due June 12.

Completion Target: December 2021

 FF Horticulture Restroom

 (Click to View Project Summary)

 

Horticulture – Phase 2 Restroom Building – Fairfield Campus

Description: New modular restroom building in orchard area.

Budget:  $401,000

Status: Construction in progress.

Completion Target: August 2018

New Science Bldg

(Click to View Project Summary)

Workzone Cam for Science Building

Science Building – Fairfield Campus

Description: New Science Building - 44,249sf

Budget: $37,600,000

Status: Construction in progress, exterior pre-cast walls erected.  Structural steel beginning in June.

Completion Target: April 2019

B100 Generator

(Click to View Project Summary)

B100 Generator for IT Center – Fairfield Campus

Description:  Provide emergency generator to support IT Center in Building 100.

Budget: $650,000

Status: New generator installed in May.  Project in close-out phase.

Construction Start Target: January 2018

Completion Target: June 2018

 B1800B Exiting Corridor

(Click to View Project Summary) 

B1800B Exiting Corridor Project – Fairfield Campus

Description:  Renovate building main corridor for code compliance.

Budget: $170,000

Status: Construction in progress.

Completion Target: August 2018

 B1800B Robotics Lab Renovation

 (Click to View Project Summary) 

B1800B Makers Space & Robotics Lab Renovation Project – Fairfield Campus

Description:  Renovate 2 existing instructional spaces for new Makers Space and Robotics Lab programs.

Budget: $450,000

Status: Maker's Space improvements nearly completed.  Robotics Lab construction in progress.

Completion Target: August 2018

Vacaville Center Active Project Updates

VV Intersection Improvements
 

(Click to View Project Summary)

Vacaville Center Intersection Improvements Project - Vacaville

Description: New signalized intersection at the Center and Annex main driveways.  Scope of work includes signalization, crosswalks, and related roadway and Annex parking lot improvements. 

Budget: $1,178,270

Status: Construction nearing completion.  Signal lights activation anticipated in June.

Completion Target: July 2018

VV Annex Classroom
 

(Click to View Project Summary)

“Annex" Classroom Building Renovation – Vacaville

Description:  Renovation of 13,940sf classroom building.

Budget:  $3,807,681

Status: Installation of fire sprinkers, ceiling gas and water lines in progress.  Gypboard patch back nearing completion.  New roofing in progress.

Construction Start Target:  January 2018

Completion Target:  August 2018

VV HVAC Upgrade
 

 (Click to View Project Summary)

Vacaville Center HVAC Upgrade – Vacaville

Description: Replacement of HVAC system at Vacaville Center Building.

Budget:  $2,315,000

Status: Construction in progress.

Construction Start Target:  April 2018

Completion Target:  August 2018