STUDENT PROJECT
STUDY QUAD

Project 5 - STUDY QUAD
TIMING
Priority: Moderate
 
BUDGET
Demolition $201,600
Pedestrian Paving $246,400
Pedestrian Lighting $21,000
Accent Lighting (22) $9,900
Fine Grading $33,600
Trees (26) $6,500
Seatwalls $62,500
Planting $15,600
Lawn $55,000
Irrigation $105,350
Signage (Directional) $5,000
Site Furniture (8 - Trash, Ash Urn, etc.) $5,600
Tables/Chairs (13) $39,000
Drainage $45,150
Drinking Fountain (3) $10,500
Subtotal - $862,700
General Conditions - 10% $86,270
Subtotal - $948,970
Bonds/Insurance - 3.5% $33,214
Subtotal - $982,184
Design Contingency - 10% $98,218
Subtotal - $1,080,402
Escalation - 6% (First Year) $64,824
Approximate Total Construction Costs $1,145,226