STUDENT PROJECT
NORTH ENTRY AT BUILDING 1300

Project 6 - NORTH ENTRY AT BUILDING 1300
TIMING
Priority: High
 
BUDGET
Demolition $33,600
Drainage $8,400
Pedestrian Accents Paving $75,000
Benches (10) $17,000
Pedestrian Lighting With Banners (10) $20,000
Accent Lighting (20) $9,000
Fine Grading $5,600
Trees (13) $3,250
Drinking Fountain $3,500
Planting $33,600
Irrigation $19,600
Signage (Campus Directory) $8,000
Site Furniture (Trash, Ash Urn, etc.) $2,800
Art N/A
Signage (Directional) $5,000
Overhead Sign $8,000
Subtotal - $252,350
General Conditions - 10% $25,535
Subtotal - $277,585
Bonds/Insurance - 3.5% $9,715
Subtotal - $287,300
Design Contingency - 10% $28,730
Subtotal - $316,031
Escalation - 6% (First Year) $18,962
Approximate Total Construction Costs $334,992