STUDENT PROJECT
AMPHITHEATER QUAD

Project 4 - AMPHITHEATER QUAD
TIMING
Priority: High
 
BUDGET
Demolition $156,900
Pedestrian Paving $273,600
Pedestrian Accent Paving $125,000
Pedestrian Lighting $19,500
Accent Lighting (20) $9,000
Fine Grading $51,275
Trees (30) $7,500
Seatwalls $172,500
Planting $17,550
Lawn $50,000
Irrigation $97,740
Drinking Fountains (4) $14,000
Site Furniture (12 - Trash) $8,400
Pond $1,200,000
Steps $240,000
Handrail $32,000
Tables & Chairs $30,000
Fountain $126,000
Fabric Structure $190,000
Outdoor Fireplace $60,000
BBQ N/A
6'-High Masonry Screen $70,000
Bell Tower $200,000
Grading $15,700
Drainage $41,890
Subtotal - $3,208,555
 
Subtotal - $3,208,555
General Conditions - 10% $320,856
Subtotal - $3,529,411
Bonds/Insurance - 3.5% $123,529
Subtotal - $3,652,940
Design Contingency - 10% $365,294
Subtotal - $4,018,234
Escalation - 6% (First Year) $241,094
Approximate Total Construction Costs $4,259,328