STUDENT PROJECT
SOUTH ENTRY TO BUILDING 100

Project 2 - SOUTH ENTRY TO BUILDING 100
TIMING
Priority: High
  BUDGET
Demolition $40,500
Pedestrian Paving $34,800
Pedestrian Accent Paving $30,000
Benches (4) $6,800
Accent Lighting (6) $2,700
Fine Grading $5,300
Trees (14) $3,500
Drainage $7,950
Planting $9,000
Drinking Fountain $3,500
Lawn $7,600
Irrigation $18,550
Signage (Directional) $5,000
Site Furniture (Trash, Ash Urn, etc.) $1,400
Steps $24,000
Walls (4' High Max.) $8,250
Handrail $7,200
Subtotal - $216,050
General Conditions - 10% $21,605
Subtotal - $237,655
Bonds/Insurance - 3.5% $8,318
Subtotal - $245,973
Design Contingency - 10% $24,597
Subtotal - $270,570
Escalation - 6% (First Year) $16,234
Approximate Total Construction Costs $286,804