STUDENT PROJECT
ENTRY AT BUILDINGS 500 AND 600

Project 1 - ENTRY AT BUILDINGS 500 AND 600
TIMING
Priority: High
 
BUDGET
Demolition of Concrete/Asphalt $27,750
Pedestrian Accent Paving $30,000
Vehicular Paving $27,000
Pedestrian Lighting (4) $6,000
Accent Lighting (2) $1,000
Trees (12 - 24" Box) $3,000
Planting $12,000
Drinking Fountain $3,500
Irrigation $7,000
Overhead Sign $8,000
Signage (Campus Directory) $8,000
Site Furniture (Trash, Ash Urn, etc.) $1,400
Fine Grading $3,500
Seat Walls $10,000
Campus Sign $5,000
Drainage $3,000
Subtotal - $156,150
General Conditions - 10% $15,615
Subtotal - $171,765
Bonds/Insurance - 3.5% $6,012
Subtotal - $177,777
Design Contingency - 10% $17,778
Subtotal - $195,554
Escalation - 6% (First Year) $11,733
Approximate Total Construction Costs $207,288